In Summer of 2017 a mid-continent operator was looking to improve production on a well in the STACK in Kingfisher Co., OK. However the well struggled to move enough gas for the ESP to efficiently produce with line pressure over 150 psig. A Flogistix rotary screw compressor was set on the casing annulus and immediately the ESP was able to handle more fluid. This resulted in a 10 bbl of oil per day increase and doubled the gas production of the well. According to the operator these production increases sustained for the next six months.

Casing Drawdown image